Project Description: Street Surface, Sidewalk, Curb and Gutter Replacement, Water Main, Sanitary Sewer Main and Storm Sewer Main in the Electric Addition
Work is on schedule. Curb, gutter and sidewalk work is in progress. Underground utility work is continuing on South Center Street, street is closed. 3rd South is closed from South 1st West to South 2nd East, local traffic and business access will be maintained
Project Description: Resurface Parking Lot and Curb and Gutter Installation at Expedition Island
Paving has been complete however the parking lot will remain closed until October 20, 2011 for park maintenance work. This project is 19 days ahead of schedule.
The public is encouraged to use additional caution when equipment is working in these areas. Call Public Works at 872-0528 with questions or concerns.