Project Description: New Mexico Street was paved on September 14, 2011.
Project Description: The Visitor Center Parking Lot was paved on September 9, 2011.
Project Description: Resurface Parking Lot and Curb and Gutter Installation at Expedition Island - The parking lot is closed. Asphalt milling and dirt work will commence the week of September 19, 2011.
Project Description: Street Surface, Sidewalk, Curb and Gutter Replacement, Water Main, Sanitary Sewer Main and Storm Sewer Main in the Electric Addition - Underground utility work is continuing on South Center Street. 3rd South is closed from South 1st West to South 2nd East, local traffic and business access will be maintained.
Traffic is detoured from East 2nd South to East 3rd South.
The intersection of East 2nd South will be open after Wednesday evening, September 14, 2011.
The public is encouraged to use additional caution when equipment is working in these areas. Call Public Works at 872-0528 with questions or concerns.