While the underpass is closed, all traffic will be routed through downtown on East Flaming Gorge Way.
This phase of the project includes replacement of the driving surface, curb, gutter, and sidewalk for 950 feet from S 1st W St. to the UP driveway just east of the overpass. A 12" water line will also replace the aging 12" Asbestos Cement pipe.
Once the road is open in October, construction will continue as weather allows. We anticipate installing the street lights in November and planting trees in early spring.
This project, slated for completion in Spring of 2017, is fully funded by the sixth cent sales tax.
Questions regarding this project should be addressed to Holden Wright, Project Engineer for the City of Green River at hwright@cityofgreenriver.org or 307-872-0524.